As part of ensuring that we can achieve our ambition to supply 80% of our electricity from renewables by 2030, NISA has been positioned as one of seven offshore wind energy projects that will be able to submit a planning application in the first round of projects to be considered under the new Maritime Area Planning Act.

Timeline

2019

Initial Consultation & Feasibility

2020

Advanced Concept Stage

2021

Consultation & EIA Appointment

2021

Public Engagement

2022

Offshore Surveys

2022

Public Engagement

2022 / 23

Receive Survey Information

2023

Consideration of survey info

2023

Engagement with Planning & Local Authorities

2023

Q1 Design Review - Establish design layout

2023
Public Engagement

CLO / Virtual consultation / Public consultation events

2023

Q3 Design Review

2023

Public Engagement

CLO / Public consultation events

2023

Apply for Planning

2024

Planning Decision

2025

Commence Construction

2028

Commence Operation

This project is being developed by Statkraft Ireland.